Health Professions and Athletics Center (HPAC)

Health Professions and Athletics Center

Plans and Progress

Current Progress

Progress of the CAHA - HPAC Project 10-1-14

Activities for October (PDF with further detail)

  • Accomplishments:
    • Steel Erection - Complete
    • Breakdown and Removal of the Crane - Complete
    • Geothermal Vault Installation - Complete
    • Underground Utilities - Complete
    • Infill of Multipurpose Room East and West Walls - Complete
    • Elevated Concrete Deck and SOG Pours - Substantially Complete
    • Stairs 1, 2 and 3 Concrete Treads - Poured
    • Penthouse Mechanical & Electrical Housekeeping Pads - Poured
    • Plumbing: Roof Drains and Rain Leaders Installation in Area A - Complete
    • Penthouse Permanent Roof - Complete
  • Upcoming Activities:
    • Bio Swale Retention Work in Lot A - Continuing Throughout into October
    • Continue Exterior Facade Framing and Application of the Air Vapor Barrier into October
    • Moving Forward with Interior Layout and Framing for the Next Couple Weeks
    • Interior CMU Walls - Complete by Mid-October
    • MEP Rough-in for Areas A and B is Ongoing
    • Mechanical Curb Installation at Grating in Penthouse
    • Curtainwall Installation - Early October
  Progress of the CAHA - HPAC Project 9-1-14

Activities for September (PDF with further detail)

  • Accomplishments:
    • Area A Steel and Mechanical Penthouse Sequences 1 & 2 - Near completion
    • Area B Steel Sequences 3 & 4 - Completed
    • Area C Steel Sequences 7 & 8 - Completed
    • Area B and Area C Level 2 Slab on Deck - Complete
    • Basement Equipment Pads - Complete
    • Underground Utilities - 99% Complete
    • Geothermal Vault Final Connections - Complete
    • Permanent Generator - Set on 8/26/14
    • Infill of Multipurpose Room East and West Walls - Near Completion
    • Multipurpose and Gym High Window Bays Have Progressed with Glass to Arrive in Early September
    • Area B Stairs Have Been Erected & Poured - Rails Installation Remains
    • Roof Blocking has Begun in Area B
    • Additional Temporary Road Installed & Stair Tower for Roof Access
  • Upcoming Activities:
    • Bio Swale Retention Work in Lot A - Continuing Throughout the Summer
    • Steel Erection - To Finish Remaining Portions of Areas B (5 & 6), C (9 -12) and the High Roof Structure
    • Remaining SOG Pour for Area B - 8/28/14
    • Remaining SOMD Pours to be Complete by Mid-September
    • MEP Rough-in for Gym & Multipurpose Rooms is Ongoing
    • MEP Hangers & Overhead Rough-in - Areas A & B
    • Roof Draing & Mechanical Curb Installation
    • Permanent Roof Installation to Begin Mid-September
    • Spray Fireproofing
    • Block and Stud Infill on the South Wall of Area A, by the Penthouse
  Progress of the CAHA - HPAC Project 8-1-14

Activities for August (PDF with further detail)

  • Accomplishments:
    • Domestic Water Supply Valve Shutdown & Replacement - Complete and Operational
    • Area A SOG Pour - Completed
    • Area B foundations completed
    • Portion of Area B SOG Pour - Completed
    • Basement Floor Patching & Infill - Completed
    • Area C Foundations - Completed
    • Area C Underground MEP Utilities - 75% Complete
  • Upcoming Activities:
    • Installation of geothermal tanks and building connection - End of July / Beginning of August
    • Parking lot curb work - Continuing Through Summer
    • Asphalt Base Course in Area A - 8/01/14
    • Steel Erection - Scheduled to Begin 7/28/14
    • Area C SOG Pour - 8/01/14
    • Infill of Multipurpose Room East Wall & Misc. Openings / Settting of Masonry Door Frames
    • MEP Rough-in for Gym & Multipurpose Rooms, Including Basement
  Progress of the CAHA - HPAC Project 7-1-14

Activities for July (PDF with further detail)

  • Accomplishments:
    • Geothermal well-field horizontal installation - over 50% complete
    • Geothermal well-filed road crossing completed 6/20/14
    • Area B foundations completed week of 6/9/14
    • Lighting wiring and pole bases in parking area complete
    • Area A underground mechanical complete 6/13/14
    • Area A underground electrical 90% complete
  • Upcoming Activities:
    • Installation of geothermal tanks and building connection
    • Parking lot curb work began 6/13/14
    • Steel erection scheduled to begin 7/14/14
    • Begin underground MEP 6/9/14
    • Area C foundations to finish week of 6/23/14
    • Area B underground MEP to finish week of 6/30/14
    • Infill of multipurpose room East wall (Multipurpose SOG to follow)
    • Slab on grade Area A to pour 6/30/14
  Progress of the CAHA - HPAC Project 6-1-14

Activities for June (PDF with further detail)

  • Accomplishments:
    • Geothermal well-field installation completed incident free
    • First footings and foundation walls poured 5/5/14
    • Area A foundations completed week of 5/26/14
    • Removal of unforeseen footings completed
    • Demolition of structurally unstable mutlipurpose room wall completed
    • Site leveling / replacement of unsuitable soils completed
    • New parking lots ready for base paving
    • Basement underground plumbing completed
    • Gymnasium underground storm completed
    • Underground waterline work completed 5/26/14
  • Upcoming Activities:
    • Installation of geothermal horizontals, tank and building connection
    • Parking lot lighting to begin 6/9/14
    • Parking lot curb work to begin 6/19/14
    • Steel erection scheduled to begin 7/7/14
    • Begin underground MEP 6/9/14
    • Area B foundations to be completed 6/6/14
    • Area C foundations to start 6/9/14
    • Infill of multipurpose room East wall (Multipurpose SOG to follow)
    • Slab on grade Area A to start 6/23/14
  Progress of the CAHA - HPAC Project 5-1-14

Activities for May

  • Accomplishments:
    • Demolition is substantially complete
    • Phase 1 - building power separation is substantially complete
    • Underslab BIM drawings submitted for approval
    • Exterior skin color samples submitted for approval
    • Geothermal drilling commenced
    • Existing pool slab on grade poured
  • Upcoming Activities:
    • Mobilize concrete subcontractor to commence pouring footings
    • Complete grading subgrade of Parking Lot A
    • Continue drilling geothermal wells
    • Submit Level 1 BIM drawings for approval
  Progress of the CAHA - HPAC Project 4-1-14

Activities for April

  • Excavation/install for underground utilities
  • Complete demolition of the building structure
  • Survey the existing building for tie-in points
  • Clear topsoil from the geothermal well-field
  • Infill of the existing pool
  • Concrete slab over existing pool
  • Drilling of the geothermal well-field
  • Additional wall openings/support steel
  Progress of the CAHA – HPAC Project 3-1-14

Activities for March

  • Phase 1
    • Electrical Manhole Structures Delivered/Installed
  • Phase 2
    • Pool Infill
    • Continuation of Selective Demolition
    • North Sitework
    • Geothermal Well-Field Work will begin
    • Building Information Model (BIM) Development of Coordination Model
    • Site Concrete Demolition/Removal
  Progress of the CAHA - HPAC Project 2-15-14

Activities Completed this Month

  • Phase 1
    • Electrical Ductbanks Completed
  • Phase 2
    • Contractors Selected
    • DGS Approval of Project
    • Subcontracts Written and Executed
    • Site Fencing Completed
    • Erosion and Sediment Control Permit Approved
    • Erosion and Sediment Controls Established
    • Site Clearing Started and Completed
    • Cut/Cap/Make Safe of Building Mechanical, Electrical and Plumbing Lines Completed
    • Asbestos and Mercury Abatement Completed
    • Selective Demolition Started

Activities For Next Month

  • Phase 1
    • Electrical Manhole Structures Delivered/Installed
  • Phase 2
    • Pool Infill
    • Continuation of Selective Demolition
    • North Sitework
    • Geothermal Well-Field Work will Begin
    • Building Information Model (BIM) Development of Coordination Model
    • Site Concrete Demolition/Removal
  Progress of the CAHA - HPAC Project 1-15-14
  • Design Phase Completed
  • Phase 1 Construction - Site Utilities in progress
  • Phase 2 Construction - Demo/Construction/Addition
    • Fence to be in placed by Friday, January 17th 2014
    • Parking Lot A will be closed during the construction phase of the project
    • Existing bus stop to be moved to TPAC Entrance (small circle - see plan)
    • 2-10-14 - The sidewalk to the south of the PE building between the Daycare Center and the Administration building is now reopened.